This is a long-term project. The proposed action is expected to be built in phases because funding will not likely come in one lump sum. Funding would be received over many years; the project would be implemented in logical, constructible pieces.
Key project timeline estimates include the following:
- The EA is anticipated to be available for review in late spring 2010.
- One public hearing to occur during the 30-day review period.
- The FHWA will then issue a decision, which is anticipated in 2010.
- The construction of the proposed action will occur over time as funding becomes available, based on Pikes Peak Area Council of Governments (PPACG) regional prioritization.
- The Powers Boulevard/Airport Road interchange is the first priority in the PPACG long-range plan. CDOT plans to have the project ready as soon as construction money becomes available.